Alward government bungles first test of so-called world class shale gas regulations

FREDERICTON-- “Premier Alward’s world-class regulations on shale gas mining have failed their first major test,” says Dr. Jean Louis Deveau, chair of the Fredericton Chapter of the Council of Canadians.

On February 7th, Corridor Resources registered with the government’s Environmental Impact Assessment (EIA) registry a proposal to propane frack four exisiting wells in Penobsquis sometime in July. This is Phase III of a three-phase project. Corridor’s short announcement was published in one small newspaper on February 11, but apparently nowhere else. The word fracking did not appear in the newspaper ad.

Before 2010, shale gas companies were not required to register for an EIA until ready to drill and frack wells. “But public pressure forced the Alward government to change that, so they created a new category of EIA called a ‘phased EIA,’ which now requires companies to register each phase of a project for an EIA.”

“The problem is this ‘phased EIA’ process is not designed to require a company to submit a formal environmental impact assessment which would trigger public hearings on their proposal,” says Deveau.

Deveau points out that until February 21st, there was nothing in the government’s EIA registry to suggest that fracking would be taking place. Nor was Corridor's proposal initially available on-line. “We live in the information age,” says Stanley resident Lawrence Wuest, “but I had to physically drive to the Department of Environment to read about the details of Corridor's proposal.”

In addition, according to a floodplain map of New Brunswick, two of the wellpads scheduled for fracking by Corridor lie on the 20 year floodplain of the Kennebecasis River. Corridor’s EIA registration document, now available on its own website does not appear to take this into consideration. This is problematic as the new rules for industry released in February 2013 place restrictions on shale gas mining in floodplains.

Energy Minister Craig Leonard even said last September that shale gas mining in flood zone areas would have to go “through a full EIA." The phased EIA now underway will likely allow Corridor to frack without any of us ever knowing how the public and the waters of the Kennebecasis River are to be safeguarded in the event of flooding," said Deveau.

“This is a far cry from what New Brunswickers should be expecting from so called ‘world-class’ shale gas regulations,” says Deveau. “I encourage New Brunswickers to demand that a comprehensive environmental impact assessment be conducted on this fracking project.”
 © 2018 NBEN / RENB